Section MIII - MC - 15 to MIII - MC 16 - Mizia/NBU

Section MIII - MC - 15 to MIII - MC 16 - Mizia/NBU

Sofia Metro Extension Project, Third Metro Line - Botevgradsko Shosse Blvd. - Vladimir Vazov Blvd. - Central part of the city - Ovcha Kupel residential area, stage II with four metro stations; separate position № 2 - near MC 18 with 2 metro stations - working shaft for implementation of TU under NATM

Client
SOFIA MUNICIPALITY / "METROPOLITEN" Jsc.
Architecture
BIAS-M Ltd, arch.Evangelina Sirakova
Main contractor
METROBUILD WEST ASSOCIATION
Facility length
900 m
Design
Complex design
Technologies and features
- metro tunnel built by Top-Down method on slotted walls, monolithic reinforced concrete
- ventilation system (VU) - partially Top-Down, partially open method, monolithic reinforced concrete
- tunnel section built in an open way from monolithic reinforced concrete
Phase/stage
in operation since 2021